Timeline!
25/01/2014 - Land purchased
08/02/2014 - Tender received from Beechwood
10/02/2014 - Deposit paid to Beechwood
24/04/2014 - Tender Variation 1
25/05/2014 - Tender Variation 2 & first drawn plans
19/06/2014 - Tender Variation 3
01/08/2014 - Land registered with council
20/08/2014 - Plans submitted to council
23/08/2014 - Tile selections completed
03/09/2014 - Plans approved by council
29/09/2014 - Colour selections done
05/10/2014 - Contract signed & sent back to head office
21/10/2014 - Commencement letter received - 28 day countdown begins!
11/11/2014 - Land cut and fence arrived
24/11/2014 - Piering completed
27/11/2014 - Plumbing completed
28/11/2014 - formwork for slab done
01/12/2014 - slab poured
05/12/2014 - External plumbing completed
15/12/2014 - Frames up & most of the windows installed
16/12/2014 - Trusses completed & sliding glass door and stacker door installed
07/01/2015 - Colorbond roofing started
08/01/2015 - Colorbond roof complete
22/01/2015 - Bricks arrived
03/02/2015 - Bricks started
09/02/2015 - Plumbing Rough in
22/02/2015 - Bricks finished
03/03.2015 - Eaves & Sliding door frames delivered
04/03/2015 - Eaves started
05/03/2015 - Eaves finished & sliding door frames installed
06/03/2015 - Gas rough in
10/03/2015 - Electrical rough in started
11/03/2015 - Electrical rough in complete & insulation delivered
13/03/2015 - Insulation installed
15/03/2015 - Gyprock installed (except alfresco)
18/03/2015 - Setting of plaster
20/03/2015 - Second coat finished
25/03/2015 - Cornices installed and waterproofing completed
02/04/2015 - Lock up & Kitchen installed
13/04/2015 - Door architraves, doors and window sills started
15/04/2015 - Skirting, all wardrobe & storage shelving, door & window frames complete
16/04/2015 - Stone bench tops installed
18/04/2015 - Screed complete
23/04/2015 - Tiling started
02/05/2015 - Tiling complete
04/05/2015 - Painter started
11/05/2015 - Plumbing rough in, toilets installed, electrical rough in started
11/05/2015 - Appliances installed
07/01/2015 - Colorbond roofing started
08/01/2015 - Colorbond roof complete
22/01/2015 - Bricks arrived
03/02/2015 - Bricks started
09/02/2015 - Plumbing Rough in
22/02/2015 - Bricks finished
03/03.2015 - Eaves & Sliding door frames delivered
04/03/2015 - Eaves started
05/03/2015 - Eaves finished & sliding door frames installed
06/03/2015 - Gas rough in
10/03/2015 - Electrical rough in started
11/03/2015 - Electrical rough in complete & insulation delivered
13/03/2015 - Insulation installed
15/03/2015 - Gyprock installed (except alfresco)
18/03/2015 - Setting of plaster
20/03/2015 - Second coat finished
25/03/2015 - Cornices installed and waterproofing completed
02/04/2015 - Lock up & Kitchen installed
13/04/2015 - Door architraves, doors and window sills started
15/04/2015 - Skirting, all wardrobe & storage shelving, door & window frames complete
16/04/2015 - Stone bench tops installed
18/04/2015 - Screed complete
23/04/2015 - Tiling started
02/05/2015 - Tiling complete
04/05/2015 - Painter started
11/05/2015 - Plumbing rough in, toilets installed, electrical rough in started
11/05/2015 - Appliances installed